Released November 01, 2013 | PERTH, AUSTRALIA
en
Researched by Industrial Info Resources Australia (Perth, Australia)--The 15-megawatt (MW) Balmoral Hydro Project (BHP) development on the Hurunui River in North Canterbury, New Zealand, remains on hold after Meridian Energy Limited (Wellington, New Zealand) said it wanted to know more about the market conditions for renewable energy in the region before continuing with the project.

The Balmoral site was chosen because of its proximity to the local transmission grid, which could eventually avoid transmission losses and also reduce electricity prices in upper South Island region; however, Meridian decided to pause project development due to the current soft demand for electricity in New Zealand.

The project originally was proposed by Ngai Tahu Property Limited (NTPL) (Christchurch, New Zealand), which owns 8,596 hectares of land adjoining and adjacent to the Hurunui River, of which 8,037 hectares is in Balmoral Forest on the north bank. NTPL investigated the options to build the Balmoral hydro-generation scheme and conducted prefeasibility studies in 2005. In 2008, Meridian Energy entered into a joint venture with NTPL and conducted technical feasibility studies.

The project would operate largely as a run-of-river scheme and generate approximately 15 MW of electricity. Ngai Tahu Property and Meridian applied for resource consents in December 2012, and the project was put on hold due to regional planning issues.

The resource consent application process will be performed during or after 2016, while the construction timeline depends on market demand. According to a project spokesperson at Meridian, the company has delayed development of several windfarms in New Zealand, including the 75-MW Hurunui windfarm in the same region. The Hurunui windfarm is still in the early scoping phase, and construction is not expected to begin at least for another four to five years.

View Plant Profile - 3034413 3072291
View Project Report - 300042964 300090255

Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, three offices in North America and nine international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle™, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
IIR Logo Globe

Site-wide Scheduled Maintenance for September 27, 2025 from 12 P.M. to 6 P.M. CDT. Expect intermittent web site availability during this time period.

×
×

Contact Us

For More Info!