Phillips 66 will restart the 14,000-barrel-per-day (BBL/d) Hydrofluoric Alkylation (HF alky) Unit at its 146,000-BBL/d refinery in Borger, Texas, this weekend, as issues continue with the 78,000-BBL/d Gas Oil Hydrodesulfurizer Unit 42. The latter unit also is expected to be restarted this weekend, after which the 41,000-BBL/d Crude 9, 37,000-BBL/d Crude 10, 68,000-BBL/d Crude 28 units and 30,000-BBL/d Fluid Catalytic Cracker Unit (FCCU) 40 will fully restart.