Power
Colombia's EPM Ituango Approves $380 Million Capitalization for 2,400-Megawatt Hydro Project
At a May 18 shareholders meeting, EPM Ituango SA ESP (Medellin, Colombia) approved capital funding of about $380 million to finance the initial work on the 2,400-megawatt...
Released Wednesday, June 01, 2011
![]() |
Español |
This capital injection secures the execution of the 2011 planned work on the project, including the construction of the civil camps for the workers and the deviation of the Cucuana River to allow the construction of the dam in 2012.
On March 30, EPM Ituango signed a build, own, operate, maintenance and transfer contract for 50 years with the former developer of the project, Hidroelectrica Ituango SA ESP (Hidroituango) (Medellin). In turn, EPM Ituango will rely on its parent company Empresas Publicas de Medellin (EPM) (Medellin), which holds 97.13% of EPM Ituango shares, for the execution of the project. With the signing of the contract, Hidroituango transferred all previously signed contracts and the ongoing tender processes to EPM Ituango.
The power plant, which is officially named the Pescadero Ituango "Jose Tejada Saenz" hydropower plant, will consist of a 225-meter-high dam with a 79-kilometer-long reservoir between the cities of Briceño and Ituango, and a powerhouse with eight 300-MW Francis hydro turbine-generator sets.
The project will be executed in two phases. In the first phase, EPM Ituango will construct the entire civil infrastructure and will install four of the eight turbines, providing an installed capacity of 1,200 MW. This phase is scheduled to be completed by 2018. In the second phase, the remaining turbines will be installed, reaching 2,400 MW of installed capacity.
At the moment, access roads are under construction, and EPM Ituango expects to select a civil contractor in the next couple of weeks for the construction of the civil camps and the deviation works. During the remainder of this year, the main civil works and the electro-mechanical component of the project will be tendered.
Colombia relies heavily on hydropower generation, with about 70% of its generation coming from hydropower. Currently, there are several hydro projects in different stages of development, with Pescadero-Ituango being the most important. The main hydro projects under construction are:
- the 820-MW Sogamoso hydropower plant (Santander) of Isagen SA ESP (Medellin)
- the 400-MW El Quimbo hydropower plant (Huila) of Emgesa SA ESP (Bogota)
- EPM's 670-MW Porce III hydropower plant in Antioquia
View Plant Profile - 1079493 1049636 1080202 1042346 1090037 1061556 1061563 3014848
View Project Report - 68000114 300023844 68000079 68000115 68000060 200005664 68000096 68000097 300021115
Industrial Info Resources (IIR) is a marketing information service specializing in industrial process, energy and financial related markets with products and services ranging from industry news, analytics, forecasting, plant and project databases, as well as multimedia services.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Learn MoreRelated Articles
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Learn MoreIndustry Intel
-
2026 Regional Chemical Processing OutlookOn-Demand Podcast / Mar. 2, 2026
-
From Data to Decisions: How IIR Energy Helps Navigate Market VolatilityOn-Demand Podcast / Nov. 18, 2025
-
Navigating the Hydrogen Horizon: Trends in Blue and Green EnergyOn-Demand Podcast / Nov. 3, 2025
-
ESG Trends & Challenges in Latin AmericaOn-Demand Podcast / Nov. 3, 2025
-
2025 European Transportation & Biofuels Spending OutlookOn-Demand Podcast / Oct. 27, 2025