Germany's Vohburg Refinery to Begin Maintenance Turnaround in March

Bayernoil Raffineriegesellschaft mbH is planning to perform a 22-day shutdown beginning on March 1 at the 120,000-barrel-per-day (BBL/d) Bayernoil Vohburg Refinery in Germany.


Researched by Industrial Info Resources (Sugar Land, Texas)--Bayernoil Raffineriegesellschaft mbH is planning to perform a 22-day shutdown beginning on March 1 at the 120,000-barrel-per-day (BBL/d) Bayernoil Vohburg Refinery in Germany. The maintenance turnaround will involve a change of catalysts, and minor repairs will be made on the 18,000-BBL/d fluid catalytic cracking unit, the 30,000-BBL/d Naphtha Desulfurization 1, the 16,000-BBL/d Reformer 1, the 1,400-BBL/d mid-distillate unit and a new selective hydrogenation unit. The remaining processing units will be kept online. The last overhaul at Vohburg site took place in the third quarter of 2003.

Bayernoil Raffineriegesellschaft operates two independent sites: Vohburg and Neustadt. The latter plant performed its last overhaul in 2008 as part of the $381.8 million ISAR project, which was implemented to optimize the refinery's facilities in the area and to increase the profitability of the Vorhburg and Neustadt refineries. One of the goals of the ISAR project was to design and build three units at the 120,000-BBL/d Neustadt site: a new 48,000-BBL/d hydrocracker, a new steam methane reformer for the production of hydrogen and a 160-ton-per-day Claus unit. The plant underwent a 26-day maintenance overhaul from April 14 to May 9, 2008, and all of the remaining processing units were revamped. Uhde GmbH (Dortmund, Germany) handled the design and construction of the hydrocracker, which began processing on December 24, 2008. The Jacobs Engineering Group (NYSE:JEC) (Pasadena, California) was in charge of the Claus unit, which started operation in September 2008, and UOP, a Honeywell (NYSE:HON) (Morris Town, New Jersey) company, designed and built the steam methane reformer, which began processing in August 2008. For more details view January 29, 2009, new article - Project ISAR at Bayernoil Refinery: New Site Structure.

The Neustadt Bayernoil Refinery is scheduled to undergo its next turnaround in the third quarter of 2011 for general maintenance work.

View Plant Profile -
1083108 1083069

Industrial Info Resources (IIR) is a marketing information service specializing in industrial process, energy and financial related markets with products and services ranging from industry news, analytics, forecasting, plant and project databases, as well as multimedia services.
/news/article.jspfalse
Share This Article
Want More IIR News?

Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 11 + 2?
Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Learn More
Industrial Project Opportunity Database and Project Leads

Get access to verified capital and maintenance project leads to power your growth.

Learn More
Industry Intel


Explore Our Coverage

Industries


  • Electric Power
  • Terminals
  • Pipelines
  • Production
  • Alternative Fuels
  • Petroleum Refining
  • Chemical Processing
  • Metals & Minerals
  • Pulp, Paper & Wood
  • Food & Beverage
  • Industrial Manufacturing
  • Pharmaceutical & Biotech

Trending Sectors


  • Data Centers
  • Semiconductors
  • Battery Supply Chain
  • Packaging
  • Nuclear Power
  • LNG
IIR Logo Globe

Site-wide Scheduled Maintenance for September 27, 2025 from 12 P.M. to 6 P.M. CDT. Expect intermittent web site availability during this time period.

×
×

Contact Us

For More Info!