Husky Energy has extended planned maintenance for six major units at its 165,000-BBL/d Lima, Ohio, refinery, until the end of November.
Chevron restarted the 56,000-BBL/d FCCU unit on November 13 at its 100,000-BBL/d Pasadena, Texas, refinery, that had been shut since August 30. Also shut the same day were the 7,200-BBL/d Alky 1 and the 7,200-BBL/d Alky 2 units that will be restarted in mid-December.
International
Gazprom Neft PAO has completed a planned maintenance turnaround for eight units at its 243,000-BBL/d Moscow Refinery in Russia. The turnaround started on October 18 and was completed November 9.
Preem AB has prolonged a planned maintenance turnaround at its 220,000-BBL/d Lysekil Refinery in Sweden. The plant-wide turnaround started on September 6 and was initially expected to be completed by mid-November, but has been postponed to late November due to undisclosed issues.
PAZ Oil Company Limited successfully restarted its 100,000-BBL/d Ashdod Refinery in Israel on November 13, after a planned turnaround for 10 major units that began on October 22.