NOVA Chemicals is on schedule to perform an approximately 35-day turnaround in August of the 2.8 billion-pound-per-year E3 ethylene unit at its Joffre Olfeins Plant in Alberta, Canada. Separately, due to COVID-19, NOVA has postponed an approximately 30-day turnaround of the 1.6 billion-pound-per-year E1 ethylene unit.