Boardwalk Pipeline Expands Texas, Louisiana Network
Boardwalk Pipeline Partners (NYSE:BWP) (Houston, Texas) placed a major natural gas pipeline project into service this quarter and is expanding its U.S. Gulf Coast presence in Texas and Louisiana.
Released Tuesday, May 02, 2017
Reports related to this article:
Project(s): View 4 related projects in PECWeb
Plant(s): View 3 related plants in PECWeb
Researched by Industrial Info Resources (Sugar Land, Texas)--Boardwalk Pipeline Partners (NYSE:BWP) (Houston, Texas) placed a major natural gas pipeline project into service this quarter and is expanding its U.S. Gulf Coast presence in Texas and Louisiana. Industrial Info is tracking $547 million of projects involving Boardwalk Pipeline.
Among the Boardwalk projects to be placed into service recently is the Northern Supply Access Project, by Texas Gas, a subsidiary of Boardwalk. The project involved the shipment of gas from Ohio to Louisiana. Speaking during the company's latest quarterly earnings presentation, Chief Executive Officer Stan Horton said: "We placed the Northern Supply Access project into service on March 2, and commercial service began on April 1. This is the second north-to-south project on Texas Gas that we have placed into service over the last year, and it raises our total north-to-south capacity to more than 900,000 MMBtu [million British thermal units] a day. Texas Gas is now truly a bidirectional system that allows us to maintain gas flows in the traditional south-to-north direction, while north-to-south capacity has been added."
Horton said that among the largest Boardwalk Pipeline projects currently under construction is the Coastal Bend Header pipeline in Texas, which will supply Freeport LNG's (Houston, Texas) liquefied natural gas (LNG) liquefaction and export plant in Quintana, Texas. "A tremendous amount of work is occurring on this project, which will serve the Freeport LNG facility. We have received all of our regulatory permits and all of the right-of-way has been secured and cleared," said Horton. "Construction of the 66-mile header pipeline and one of the new compressor stations has commenced. The fully contracted 1.4-billion-cubic-foor-per-day project is on schedule to be placed into service in 2018." For more information, see Industrial Info's project reports on the pipeline and grassroot compressor station involved in the project.
"We also have under way a number of projects that will serve in-use markets in Louisiana," said Horton. Among the pipeline projects in Louisiana is a grassroot natural gas compressor station and lateral addition in Montz, Louisiana. The project involves constructing a 4,700-horsepower compressor gas package and 900 feet of transmission pipeline to provide up to 133 million standard cubic feet per day of natural gas to an existing pipeline system in southeast Louisiana. "We anticipate that service for the compressor station and minimal amount of new pipe will begin in early 2018," said Horton of the project. For more information, see Industrial Info's project report.
In addition to pipeline projects in Louisiana, Boardwalk is also converting a natural gas storage cavern in Plaquemine, Louisiana, to hold natural gas liquids (NGL). The project will convert the existing 6.67 billion-cubic-foot natural gas storage cavern to NGL storage. The $50 million project is planned to kick off this summer and be completed by the end of the year. For more information, see Industrial Info's project report.
Boardwalk reported first-quarter 2017 net income of $119.3 million, compared with $101 in the same period last year. The company is planning $850 in total capital spending this year, with $710 million planned for growth projects.
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, five offices in North America and 10 international offices, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities. Follow IIR on: Facebook - Twitter - LinkedIn. For more information on our coverage, send inquiries to info@industrialinfo.com or visit us online at http://www.industrialinfo.com.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Learn MoreRelated Articles
-
Pipeline Completed for Cameron LNG Facility in LouisianaMarch 16, 2018
-
Boardwalk Pipeline Trims Capital Spending for 2018 After Rev...February 13, 2018
-
Boardwalk 50% Complete on Freeport LNG Gas FeedAugust 01, 2017
-
Boardwalk Pipeline Beefs up 2017 Capex to $850 MillionFebruary 15, 2017
-
Boardwalk Pipeline to Invest $850 Million in Capex for 2016February 09, 2016
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Learn MoreIndustry Intel
-
2026 Regional Chemical Processing OutlookOn-Demand Podcast / Mar. 2, 2026
-
From Data to Decisions: How IIR Energy Helps Navigate Market VolatilityOn-Demand Podcast / Nov. 18, 2025
-
Navigating the Hydrogen Horizon: Trends in Blue and Green EnergyOn-Demand Podcast / Nov. 3, 2025
-
ESG Trends & Challenges in Latin AmericaOn-Demand Podcast / Nov. 3, 2025
-
2025 European Transportation & Biofuels Spending OutlookOn-Demand Podcast / Oct. 27, 2025