Gezhouba Group Completes Dam Plinth and Abutment Excavation for China Guodian's Houziyan Hydropower Station
China Gezhouba Group No.1 Engineering Company Limited completed the dam plinth and abutment excavation for China Guodian Corporation's 1,700-megawatt Houziyan Hydropower Station
Released Wednesday, April 24, 2013
Reports related to this article:
Project(s): View 1 related project in PECWeb
Plant(s): View 1 related plant in PECWeb
Researched by Industrial Info Resources China (Beijing, China)--China Gezhouba Group No.1 Engineering Company Limited (Yichang, Hubei), a subsidiary of China Gezhouba Construction Group (CGGC) (Yichang, Hubei), completed the dam plinth and abutment excavation for China Guodian Corporation's (Beijing) 1,700-megawatt (MW) Houziyan Hydropower Station ahead of schedule on April 6, 2013, according to an announcement from the CGGC on April 17.
The Houziyan Hydropower Station, located in Kangding County of the Garze Tibetan autonomous prefecture, is the ninth cascade project planned on the main stream of the Dadu River, a tributary of the Changjiang River in southwest China's Sichuan province. It is also a key project planned in the nation's 11th Five-Year Energy Development Plan (2006-2010); a key project in supporting the economic and social development for the Tibetan living area in Sichuan; and one of the 23 key projects listed in the nation's western development program.
The project mainly involves a 223.5-meter-high concrete face rockfill dam, the second-highest of its kind in China, with a total reservoir capacity of 704 million cubic meters and a powerhouse furnished with four hydraulic turbine generating units, each of 425 MW.
Guodian Dadu River Hydropower Development Company Limited (Chengdu, Sichuan), a subsidiary of GD Power Development Company Limited (SHA:600795) (Beijing), the listed flagship of China Guodian Corporation, is responsible for the development and future operation of the project. HydroChina Chengdu Engineering Corporation (Chengdu) is responsible for the design and engineering of the project.
The project received final approval from the National Development and Reform Commission (NDRC) on November 8, 2011. Construction of main works for the project then kicked off. According to the schedule, the first unit of the project is expected to begin operation in July 2016, and the whole project is expected to begin operations in 2017.
Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp
false
Want More IIR News Intelligence?
Make us a Preferred Source on Google to see more of us when you search.
Add Us On GoogleAsk Us
Have a question for our staff?
Submit a question and one of our experts will be happy to assist you.
Forecasts & Analytical Solutions
Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.
Learn MoreRelated Articles
-
Indonesia to Build Two Floating Solar PlantsDecember 28, 2022
-
EIA: Renewables to Become Leading Source of World Energy Con...October 03, 2019
Industrial Project Opportunity Database and Project Leads
Get access to verified capital and maintenance project leads to power your growth.
Learn MoreIndustry Intel
-
2026 Regional Chemical Processing OutlookOn-Demand Podcast / Mar. 2, 2026
-
From Data to Decisions: How IIR Energy Helps Navigate Market VolatilityOn-Demand Podcast / Nov. 18, 2025
-
Navigating the Hydrogen Horizon: Trends in Blue and Green EnergyOn-Demand Podcast / Nov. 3, 2025
-
ESG Trends & Challenges in Latin AmericaOn-Demand Podcast / Nov. 3, 2025
-
2025 European Transportation & Biofuels Spending OutlookOn-Demand Podcast / Oct. 27, 2025