GAIL's Kochi-Koottanad-Bangalore-Mangalore Pipeline Project Progresses on Schedule

GAIL India Limited is progressing with Phase I of the Kochi-Koottanad-Bangalore-Mangalore pipeline and is expected to complete the project by October 2012.

Released Friday, January 06, 2012

GAIL's Kochi-Koottanad-Bangalore-Mangalore Pipeline Project Progresses on Schedule

Researched by Industrial Info Resources India (Delhi, India)--Indian gas major GAIL India Limited (BSE:532155) (New Delhi) is progressing with Phase I of the Kochi-Koottanad-Bangalore-Mangalore pipeline and is expected to complete the project by October 2012. Phase I involves laying 26 kilometers of 30-inch pipeline from Kochi-Koottanad at a cost of $11 million.

In Phase II, pipelines will be laid from Kochi to Alwaye and Mangalore, as well as from Palghat to Bangalore, at a cost of $200 million. The first phase is expected to be completed by October 2012, and Phase II is scheduled to be completed two months later.

Phase I is progressing according to the schedule. Acquisition of Right of User (RoU) has been completed and permission has been obtained for crossing obstacles. All orders have been placed and the manufacturing and coating of bare lines has been completed. Phase I originally was scheduled to be completed by March 2012, but is now planned to be completed by October 2012, in sync with the commissioning of the liquefied natural gas (LNG) terminal at Kochi.

Phase II is also on schedule. A detailed route survey has been completed and notification of the Petroleum & Mineral Pipelines Act (the acquisition of RoU in land) has been published for the entire pipeline. Out of a total of 1,189 permissions required under Phase II, as many as 812 permissions have been received as of December 2011. A total of 465 kilometers of bare pipe has been manufactured, and 270 kilometers of pipe has been coated. The contract for pipeline laying works is yet to be awarded.

View Project Report - 300030728 300032089

Industrial Info Resources (IIR), with global headquarters in Sugar Land, Texas, and eight offices outside of North America, is the leading provider of global market intelligence specializing in the industrial process, heavy manufacturing and energy markets. Industrial Info's quality-assurance philosophy, the Living Forward Reporting Principle™, provides up-to-the-minute intelligence on what's happening now, while constantly keeping track of future opportunities.
/news/article.jsp false

Share This Article

Want More IIR News Intelligence?


Make us a Preferred Source on Google to see more of us when you search.

Add Us On Google

Please verify you are not a bot to enable forms.

What is 81 + 1?

Ask Us

Have a question for our staff?

Submit a question and one of our experts will be happy to assist you.

By submitting this form, you give Industrial Info permission to contact you by email in response to your inquiry.

A glowing computer chip is placed on a dark blue circuit board. Bright blue lines and nodes create a futuristic, technological ambiance.

Forecasts & Analytical Solutions

Where global project and asset data meets advanced analytics for smarter market sizing and forecasting.

Explore Our Solutions
Dimly lit data center with rows of towering black server racks, glowing blue lights, and a sleek, futuristic ambiance.

Industrial Project Opportunity Database and Project Leads

Get access to verified capital and maintenance project leads to power your growth.

Discover Our Database