BEIJING--May 24, 2013 - Researched by Industrial Info Resources China (Beijing, China)--Following the erection of the generator stator for Unit 1 of China Datang Corporation's (Beijing) 1,200-megawatt (MW) Huaibei Hushan Power Project on February 3, 2013, Anhui Electric Power Construction No.1 Engineering Company (AEPC1) (Hefei, Anhui), a subsidiary of China Energy Engineering Corporation (CEEC) (Beijing), erected the generator rotor for Unit 1 on May 14, according to an announcement from CEEC on May 15.
Subscribe Now!(All Fields Required)
Related Articles
Articles related to this company
- Datang Huaibei Power Plant's Hushan Coal-fired Project Begins Full Operatio...
- Unit 1 of China Datang's Hushan Coal-fired Power Project Begins Operations
- AEPC2 Completes Steam Turbine Box-Up for Unit 2 of Huaibei Hushan Power Pro...
- AEPC2 Completes Stator Erection for Unit 2 of Datang Huaibei Hushan Power P...
- AEPC1 Completes Generator Stator Erection for Unit 1 of Datang Huaibei Hush...