First Unit of Tianji Power Plant Expansion Begins Initial Operations

First Unit of Tianji Power Plant Expansion Begins Initial Operations

First Unit of Tianji Power Plant Expansion Begins Initial Operations

BEIJING--December 13, 2013--Researched by Industrial Info Resources China (Beijing, China)--The first unit (Unit 3) of the 1,320-megawatt (MW) Phase II expansion project at the Tianji Power Plant was connected to the grid on December 8, 2013, according to an announcement from Anhui Electric Power Construction No.1 Engineering Company (AEPC1) (Hefei, Anhui), the construction and erection contractor for the project and a subsidiary of China Energy Engineering Corporation (CEEC) (Beijing).