First Unit of Zhongtai Chemical's Power Station for Calcium Carbide Project Begins Operations

First Unit of Zhongtai Chemical's Power Station for Calcium Carbide Project Begins Operations

First Unit of Zhongtai Chemical

BEIJING--October 17, 2012--Researched by Industrial Info Resources China (Beijing, China)--Following the connection to the grid on September 14, 2012, the first unit of Xinjiang Zhongtai Chemical (Group) Company Limited's (Urumqi, Xinjiang) 600-megawatt (MW) power station for its 1 million-metric-ton (MMT) Calcium Carbide Project passed the 72+24-hour, continuous, full-load trial operation and was handed over for commercial operations on September 27, 2012, according to a recent announcement from Central Southern Electric Power Design Institute (CSEPDI) (Wuhan, Hubei), the general contractor of the project and a regional subsidiary of China Power Engineering Consulting Corporation (CPECC) (Beijing).