BEIJING--October 11, 2013--Researched by Industrial Info Resources China (Beijing, China)--Anhui Electric Power Construction No.1 Engineering Company (AEPC1) (Hefei, Anhui), a subsidiary of China Energy Engineering Corporation (CEEC) (Beijing), completed the erection of the first steel beam for Unit 4's boiler mainframe for Huadian Luan Power Generation Company Limited's (Luan, Anhui) 1,320-megawatt (MW), coal-fired expansion project at the Luan Power Plant.